ECO-3 Protecting Our Soil, Water & Air Erosion & Sediment Control Training & Site Supervision
|
|
EPA Stormwater Requirements in the State of Oregon
EPA Construction
General Permit (CGP) Section 9
a)
Confederated Tribes of the Umatilla Indian Reservation. The following conditions
apply only for projects within the exterior boundaries of the Umatilla Indian
Reservation:
i)
The operator shall be responsible for achieving compliance with the Confederated
Tribes of the
ii)
Umatilla Indian Reservation’s (CTUIR) Water Quality Standards.
iii)
The operator shall submit all Erosion Control and/or Storm Water Pollution
Prevention Plans to the CTUIR Water Resources Program for review and approval by
the Department of Natural Resources Director prior to submitting the Notice of
Intent to EPA and prior to beginning any discharge activities.
iv)
The operator shall contact the CTUIR Tribal Historic Preservation Office (THPO)
prior to beginning any construction activities to determine whether a cultural
resource survey of the project area or other investigation is required. All
cultural resource fieldwork must be conducted by qualified personnel and
documented using Oregon Reporting Standards. The resulting report must be
submitted to the THPO for concurrence at least 30 days before any ground
disturbing work can occur at the site. The operator must obtain THPO concurrence
in the form of a letter, which (if necessary) will include any measures that
must be taken to prevent or mitigate adverse effects to potentially eligible
historic properties, prior to any ground disturbing work.
v)
The operator shall submit copies of the Notice of Intent to the CTUIR Water
Resources Program and the CTUIR Tribal Historic Preservation Office at the same
time it is submitted to EPA.
vi)
Erosion Control and Storm Water Pollution Prevention Plans and Notices of Intent
shall be submitted to:
Confederated Tribes of the Umatilla Indian Reservation
Water Resources Program
P.O. Box 638
Pendleton, OR 97801
(541) 276-3447
Confederated Tribes of the Umatilla Indian Reservation
Cultural Resources Protection Program
Tribal Historic Preservation Office
P.O. Box 638
Pendleton, OR 97801
(541) 276-3629
b)
Confederated
Tribes of Warm Springs. The following conditions apply only for projects on the
Warm Springs Indian Reservation:
i)
All activities covered by this NPDES general permit occurring within a
designated riparian buffer zone as established in Ordinance 74 (Integrated
Resource Management Plan or IRMP) must be reviewed, approved and permitted
through the Tribe’s Hydraulic Permit Application process, including payment of
any applicable fees.
ii)
All activities covered by this NPDES general permit must follow all applicable
land management and resource conservation requirements specified in the IRMP. iii) Operators of activities covered by this NPDES general permit must submit a Storm Water Pollution Prevention Plan to the Tribe’s Water Control Board at the following address for approval at least 30 days prior to beginning construction activity:
Chair, Warm Springs Water Control Board